亚洲аv天堂无码,久久aⅴ无码一区二区三区,96免费精品视频在线观看,国产2021精品视频免费播放,国产喷水在线观看,奇米影视久久777中文字幕 ,日韩在线免费,91spa国产无码

      China accelerates Uganda's green energy drive to fast-track development

      Source: Xinhua| 2019-02-27 20:19:27|Editor: ZX
      Video PlayerClose

      KAMPALA, Feb. 26 (Xinhua) -- Isimba Hydropower Plant constructed by Chinese companies in eastern Uganda awaits official commissioning next month after it passed tests from engineers, environmentalists and conservationists.

      After commissioning of all the units, the Isimba power plant will generate the installed capacity of 183 MW, which is currently about 19 percent of the country's power generated. The country generates up to 974.84 MW, which experts say is inadequate and expensive.

      Constructed along the Nile, the world's longest river, the power plant comes in time to save the country from the thermal-generated electricity of high tariff.

      At the peak of the power crisis in 2014, Uganda's government resorted to using diesel generators to power the country's economy, which raised the cost of power.

      According to Uganda Electricity Transmission Company Limited, a state-run agency, the cost of thermal power per unit then ranged from 25.28 U.S. cents to 27.08 cents. The cost for hydropower was 12 cents per kWh.

      The rising of the electricity costs forced some of the manufacturers to increase the prices of their products.

      The intermittent power supply also forced some manufacturers to run their own diesel generators, which also increased their cost of production and later rendered their products not competitive because of the high price.

      Economists warned that the inadequate power supply was a key bottleneck to unlocking the country's economic potential.

      Uganda's government then resolved to increase hydropower generation in a bid to increase power supply and also reduce its cost.

      The construction of the 568-million-dollar power plant started in 2015, after the east African country secured a loan from the Export-Import Bank of China. This was one of the key green energy projects that China undertook to help Uganda fast-track its development.

      Another Chinese funded key green energy project is the 600 MW Karuma Hydropower Plant, also constructed along the Nile in northern Uganda.

      The government anticipates that both the Isimba and Karuma power plants will address the country's power shortage.

      Before construction of Isimba in 2015, the contractor China International Water and Electric Corporation (CWE) was tasked by the government's environmental watchdog, National Environment Management Authority (NEMA), to do an environmental impact assessment.

      After wide consultations from responsible government departments, environmentalists, conservationists, academicians and the community that was going to be affected by the project, CWE was given a go-ahead.

      "This study was relevant because we had to look at the possible impacts that the project would have on the environment, and social impact as well, and also come up with the mitigation measures before the implementation," Nancy Allimadi, a NEMA official, told Xinhua in a recent interview.

      Throughout the construction period, a government multisectoral task force subjected the project to tests and monitoring on a quarterly basis.

      "We are going towards the commissioning of the project and we have not had any major environmental damage," she added.

      Allimadi said CWE worked with the committee to address any concerns that came up, adding that working with CWE showed that Chinese contractors are putting into consideration environmental concerns in their projects.

      "We are pleased that the contractor was listening, we never had any challenging time," said Allimadi, noting that in case any concerns came up they would sit together and devise solutions.

      As Isimba nears commissioning, CWE requested Uganda Wildlife Authority (UWA), a state-run conservation agency, to relocate the wildlife that was going to be affected.

      Bashir Hangi, UWA's spokesperson, told Xinhua recently that a total of 109 wild animals categorized in nine different species, which among others included snakes and monkeys, were safely rescued and released to a new habitat at neighboring Mabira Forest.

      "It was important to relocate the said wildlife species for their protection as their safety could not be guaranteed anymore. We want energy, and developers undertook a detailed environmental and social impact assessment. This assessment usually has proposed measure to mitigate against the impacts of the project. As for wildlife, we relocated the species that were there," Hangi said.

      TOP STORIES
      EDITOR’S CHOICE
      MOST VIEWED
      EXPLORE XINHUANET
      010020070750000000000000011100001378551291
      主站蜘蛛池模板: 白嫩少妇激情无码| 免费在线日韩| 探索| 成年女性毛片在线观看| 欧美韩国精品另类综合| 亚洲在战AV极品无码| 久久精品国产亚洲AV无码偷窥| 伊人色综合视频一区二区三区| 精品91精品91精品国产片| 国产一区二区三区在线免费观看| 不卡无毒免费毛片视频观看| 影音先锋每日av色资源站 | 国产精品视频啊啊| 99国产综合精品-久久久久| 国产成人内射视频免费观看| 国产一线视频在线观看高清| 超薄肉色丝袜一区二区| 91福利国产在线观看网站| 亚洲传媒av一区二区三区| 日韩精品极品视频在线观看蜜桃 | 日本中文字幕不卡在线一区二区| 天堂中文在线www天堂在线| 国产成人亚洲精品狼色在线| 亚洲最新中文字幕一区| 亚洲男人堂色偷偷一区| 三级黄色片一区二区三区| 产国语一级特黄aa大片| 91啪在线| 久久露脸国产精品WWW| 临潭县| 免费一区二区三区视频狠狠| yy亚洲人成电影网站色| 亚洲熟妇av一区| 国产激情啪啪自拍视频| 国产高清在线精品一区αpp| 欧洲熟妇性色黄| 色综合狠狠操| 榆树市| 日韩欧美一卡2卡3卡4卡无卡免费2020 | 国产精品青青在线麻豆| 远安县|